top of page
  • sensinglocal

Mid-Level Project Update

Date: 12th June, 2021

Number of Attendees: 22


A mid-project meeting was held after the completion of Phase I of the project - Planning and Assessment. The findings of the from the on-ground surveys, interviews and audits of the Planning and Assessment stage were shared with the community. Following this, the draft masterplan, design details and visualisations of the proposed interventions were also shared. The purpose of the meeting was to receive feedback on the draft designs and plan the way forward for implementation. You can view the The Minutes of the Meeting here.



17 views0 comments

Recent Posts

See All

Dates: February to April, 2021 Survey Location: Doddanekundi (Ward 81, 82 and 85) Number of citizens surveyed: 971 (523 M, 448 F) Summary: A detailed house hold survey was conducted to understand the